Olympic Stadium


Client: Team Stadium (Sir Robert McAlpine)
Value: £3m
Programme: 15 months
Consultant: Buro Happold

Olympic Stadium

E&S Heating & Ventilation Ltd were engaged to provide a full airside package to the iconic Olympic Stadium on the Olympic Park in Stratford East London. As well as the provision of all the galvanised and Flameshield fire rated ductwork E&S were responsible for the co-ordination and final plant selection and procurement of the associated ventilation equipment together with the provision of thermal insulation and commissioning. The project team had to overcome the significant security and delivery issues of working on the Olympic Park along with the additional security measures included in the design to protect VIP’s, athletes and the general public during the games.

Transformation Project (Westham Stadium)

E&S Heating & Ventilation Ltd were Imtech Meica’s domestic subcontractor (working for Balfour Beatty) for the adaptation of the ventilation services to suit its new use.

Media Press Centre, Olympic park2 300dpi INTER.jpg

Media Centre, Olympic Park, Stratford


Client: Skanska Rashleigh Weatherfoil
Value: £1.5m
Programme: 12 months
Consultant: Buro Happold

E&S Heating & Ventilation Ltd were contracted to provide galvanised and Flameshield fire rated ductwork for this new build media centre on the Olympic Park in Stratford. The building incorporated a large number of modules, constructed off site where ductwork was installed by ourselves working alongside the module manufacturers. The building was designed to cater for the large number of international journalists and the associated TV crews who used the facilities during the currency of the Olympic Games.

.

RIMG0752 (300dpi).jpg

Wimbledon Centre Court & Court 1


Client: Skanska Rashleigh Weatherfoil & Sir Robert McAlpine
Value: £2.4million & £3.6million
Programme: Both 24 Months
Consultant: Centre Court: Foreman Roberts & ME Engineers, Court 1: ME Engineers

Centre Court

E&S Heating & Ventilation Ltd was contracted to provide both galvanised and fire rated ductwork services to the back of house refurbishment and innovative new retractable roof. The back of house refurbishment presented a number of challenges to upgrade existing facilities providing office, retail, media and corporate entertainment venues within the confines of the existing structure. The new closing roof was used to great acclaim for the first time in the 2009 Championships providing a fully air-conditioned space on court. Our engineering team worked closely with both our client and the consultant to provide a concealed installation of a large amount of ductwork and associated equipment within the Centre Court roof.

Court 1

E&S Heating & Ventilation Ltd was successful in open competition and was contracted by Sir Robert McAlpine to undertake the bowl ventilation works within the Wimbledon Court 1 refurbishment.  Court 1 has been fitted with a retractable roof (as Centre Court) to enable all weather play.  The bowl ventilation works include a very complex co-ordination exercise which has been led by E&S.  The project programme is closely managed to meet the AELTCC deadlines for the championships.


02 Arena 300dpi.jpg

O2 Arena


Client: Emcor Engineering Ltd
Value: £2.94m
Programme: 12 months
Consultant: ME Engineers

Within the redevelopment of the Millennium Dome, E&S Heating & Ventilation Ltd provided the ductwork services as a traditional sub-contractor to the ME contractor. Our works included the manufacture and installation of the 2m diameter ringmain ductwork within the steel frame of the arena roof. E&S were also responsible for providing ventilation services to the concession areas within the arena and met a very demanding programme.

DSCF1308 300dpi.jpg

O2 Entertainment District


Client: Sir Robert McAlpine
Value: £3.14m
Programme: 12 months
Consultant: ME Engineers

E&S Heating & Ventilation Ltd provided the full airside package for the shell & core on all six buildings working directly for the builder Sir Robert McAlpine.

The Pitch (D) 300dpi inter 2.jpg

Emirates Stadium


Client: Sir Robert McAlpine
Value: £3.7m
Programme: 19 months
Consultant: Buro Happold

E&S Heating & Ventilation Ltd were responsible for a full airside package for the new Arsenal football stadium. The development provides a 60,000 all seater stadium with 150 executive boxes, over 900 WC’s, catering and concession facilities all of which are served by 180 supply and extract systems.


Other Industries

Click below to see our further projects

 
case-study-nph-banner.jpg

Healthcare & Education


Bio.jpg

Biomedical & Pharmaceutical


Bio.jpg

Specialist


case-study-nph-banner.jpg

Commercial